Gaurain, Belgium
2009
2011
Mine&Quarry
Limestone
No
Design, supply, installation and commissioning of two conveying lines (SAMMI job no. 2762 – Stock Pile and SAMMI job no. 2764 – Remontée Carrière) complete with hoppers, belt conveyors, transfer towers and a storage system, and revamping of some of the existing belt conveyors.
The proposed solution consists of:
Line 1 (2762) – conveying limestone (rock in sizes of 0/200-250 mm from the quarry crushers) from the existing site to the new covered storage area built by SAMMI (storage capacity of 50,000 t; dimensions of 48 m wide, 90 m long and 30 m high). Here the limestone is discharged and distributed evenly inside the store by a tripper car (engineered, manufactured and assembled by SAMMI) with a capacity of 2,500 t/h.
Line 2 (2764) – conveying the stored stone to the secondary crushing plant, up the quarry slope.